LBT together with Suzhou Oxygen Plant Co., LTD. (SOPC) achieved the successful start-up of Shahe LNG EPC Project on December 1st.
The Shahe LNG EPC Project was jointly commissioned on August 11, 2017, and was started up on 9:55, November 26, 2017 when natural gas was introduced. The EPC start-up team including the leaders and front-line personnel at all levels worked for 24 hours per day to check each system, each piece of equipment, and each joints for leakage and working condition. All the findings were immediately solved properly to ensure that the start-up goes smoothly. After 6 days and 6 nights of continuous work the plant was successful started up, and ready for turning to operation.
LBT would like to take this opportunity to thank Shahe LNG for their support at all levels and would also like to thank our cooperation partner SOPC to make this project successful.